![]() |
Clause 6 |
Question 1I have been advised by my architect that since I do not have the
said "foreman" who I advise would be on site, he is reducing
my prelims. I have however had a foreman throughout the entire project
on site be it one of my other foreman, myself and my partner in
the business. Is he legally allowed to do this based on the JBCC
contract? Ref: P06.001 |
AnswerPBA 6.1 effectively states that the contractor must have a "representative" ... continuously on site...” Note "foreman" is not used or identified in any form whatsoever. The preliminaries are adjusted [32.12] as necessary which is not the case in this instance. In my opinion the architect is not acting in terms of the Agreement and the employer would loose should the issue be taken to dispute resolution. |