![]() |
Clause 34 |
Final Account and Final Payment
Question 1The final account was prepared and issued to me the contractor after the employer informed the professional team that he was satisfied with it. I signed acceptance thereof and requested the issuing of the certificate of final completion and the final payment certificate. I have now been informed that the employer has had “second thoughts” and has changed some amounts and has requested that the “revised” final account be signed. Am I obliged to accept his action? Ref: P34.001 |
AnswerIt is a basic principle of law that a legally binding agreement cannot be changed by one party without the consent of the other. I believe that the “offer and acceptance” of the final account complies with this principle. I have no doubt that you should not accept the retraction of his “offer” and should declare a dispute which I believe you will win “hands down” I suggest that you seek legal advice in taking such action. |
Question 2The final account has been prepared and submitted to the contractor who is quibbling about ‘minor issues’, but not substantiating these to assist in finalizing the outstanding amounts. Hence the contractor is refusing to issue a VAT invoice> How can the contract be brought to a speedy, equitable conclusion? Ref: P34.002 |
AnswerAll parties must comply with the laws of the country. |
Question 3An eager professional team may complete the final account before the dates stipulated in the PBA. Are there any advantages / disadvantages ? Ref: P34.003 |
AnswerWhilst the final account can be compiled as trades complete their tasks, the issue and acceptance of project final account must follow the sequence and periods described in the contract. |
Question 4Can the principal agent issue a final account and a final completion certificate without issuing the final payment certificate ? (to sort out penalties etc) Ref: P34.004 |
AnswerThe principal agent is acting outside the parameters of the PBA and by implication the financial management act and the VAT act. |
Question 5Under what circumstances can a “final payment certificate” be withdrawn? Ref: P34.005 |
AnswerThe final and indeed any payment certificate is a liquid document entitling the contractor to apply for a court order forcing the employer to make payment. Interim certificates are deemed to be a reasonable estimate of the value of the completed works – and variations can be accommodated in subsequent certificates. The principal agent can not amend the final payment certificate by issuing subsequent certificates or by cancelling it – thus absolute caution is required when compiling this document. |
Question 6When must the contractor ‘claim’ interest? Ref: P34.006 |
AnswerThere is no stipulation in the JBCC agreements that the contractor must claim within a particular timeframe default or compensatory interest that he may be entitled to under certain circumstances. |