![]() |
Clause 31 |
Question 1We, the QS, have issued our valuation to the Principal Agent and sent copies to the Employer and Contractor. In a subsequent site inspection the Employer was expressed his disapproval of some of the workmanship and instructed that the payment related thereto must be withheld. What are the contractual implications? Ref: P31.001 |
AnswerThere is absolutely no provision in the PBA for the employer to interfere with the payment process in any manner whatsoever. Where this happens it is a serious transgression of the Agreement and provides the contractor the grounds to declare a dispute or to give notice of his intention to terminate in terms of 38.1.3,6-8 [4.1 Edition 38.1.6-7] |
Question 2The PBA does not appear to make provision for Materials off Site Cession Form. Why not? Where can I find such form? Ref: P31.002 |
AnswerJBCC does not advocate the use of a "Materials Off Site" cession form as it is almost certainly legally unenforceable thereby giving the employer a false sense of security. Where the contractor has provided a construction guarantee the cover provided in most instances is sufficient to include for this condition. If not the contractor can provide and Advance Payment Guarantee which covers this condition [31.6.5] |
Question 3Under what circumstances is the contractor entitled to exercise his lien?. The employer’s bank required that the contractor to sign their “standard” waiver form and not the JBCC form. Ref: P31.003 |
AnswerThe only circumstance that allows the contractor to exercise his lien is “Where the employer has not paid or has made partial payment only....” [31.16]. I trust that the bank’s form does not include any provisions that are not within the Agreement provisions. |
Question 4What is the status should the employer make cash deposits when settling a payment certificate in relation the significant bank charges made against cash deposits? Ref: P31.004 |
AnswerThe agreement requires the employer to make payment 31.9 and does not specify the method of doing so - cash, cheque etc. JBCC cannot set specific methods of payment so I doubt that you can recoup the cost from the employer as this method is accepted in terms of the law of the land. The best I can suggest is that in future you should qualify your tender with the proviso that payments must be electronic or by certified cheque. I too get really up tight when cash deposits are made to my account! |
Question 5Please explain the meaning of the last sentence of 31.11 in relation to the calculation of default interest. Ref: P31.005 |
AnswerI trust you have read the definition of interest as stated in 1.0. For the purpose of demonstration I am assuming the current Reserve Bank rate (commonly known as the "repo rate") stands at 10.0%. This is published on the financial page of most newspapers and is instantly available on the Web - just search for "repo rate". Note that the rate can change each month so check before calculating the default interest due. Assuming the "default" amount due = R100 000, the late payment period is 21 calendar days the calculation is as follows: In terms of 31.11 the default interest rate will be 10% x 160% = 16.0%. Therefore the total amount due is: R100 000 + (R100 000 x 16.0% x 21 / 365) = R100 920.55 Straight forward? I trust so! |
Question 6When is the contractor entitled to recover compensatory interest and how is such interest calculated? Ref: P31.006 |
AnswerThe employer’s liability for payment of compensatory interest [31.10] is based upon the fact that he now has the benefit of possession of the works, albeit only in a state necessary to meet the requirements of practical completion, whilst the contractor has not yet been paid the full contract value. Consequently the contractor is entitled to recover compensatory interest on the amounts certified in all interim payment certificates issued 31 c days after the date of practical completion subject to the value of any item still outstanding 20 w days after the issue of the works completion list being excluded for the purposes of calculating such interest [25.4]. |
Question 7Whilst in terms of my agreement with the employer specifies the 20th as the date for issue of the payment certificate the principal agent dates the certificates the 1st of the following month. Despite these circumstances is payment of the certified amount still due within 7 days of the specified date of issue of the certificate and if so when will the employer become liable for default interest on such amount? Ref: P31.007 |
AnswerThe employer is to pay the contractor the amounts certified in all interim payment certificates within 7 c days of the date for issue of the payment certificate [31.9], being the date stated in the post tender conditions [41.7] and not the date upon which it is issued or that reflected on the certificate . Where the employer fails to make such payment the contractor will be entitled to recover default interest on the amount compounded monthly at 160% of the interest rate [1.1] from the due date until the date of payment [31.11] which interest is to be included in the recovery statement [33.0]. |
Question 8In my capacity as principal agent I issued an interim payment certificate in respect of the value of completed work although before the expiry of the 7 c day period within which payment is to be made some of the work was found to be defective. In the circumstances is the employer entitled to deduct the value of such defective work from the certified amount and, if so, will I be required to issue an amended payment certificate? Ref: P31.008 |
AnswerThe employer has no right whatsoever, whether in terms of the agreement or the law, to deduct any amount from that certified in a payment certificate nor may such certificate, once issued, be amended. Failure to pay the certified amount will entitle the contractor to terminate the agreement [38.1.6]. The correct procedure would be to adjust the value certified in the next payment certificate so as to take into account the value of the defective work should this not have been rectified in the interim. |
![]() |