Clause 20 |
Question 1
Ref: P20.001 |
AnswerThere is no one distinctly definitive element as they are both specialist subcontractors. I trust that you have a copy of the Principal Building Agreement available. Compare the following clauses: 20.0 Nominated 21.0 Selected 20.1.1 No consultation with contractor 21.1.1 Consultation with contractor 20.1.2 Appointment as per 20.1.1 21.1.2 Appointment as per 21.1.1 20.7 Termination decision by PA 21.7 Termination decision by contractor 20.9 N default - Contractor compensated 21.9 Employer default - contractor compensated Open to all tenderers Limited to selected tenderers Open tender - preferred by State Limited tender - avoided by State Employer’s risk increased Contractor’s risk increased |